Attached is the FY2025 Proposed Operating and Capital Budget. The following changes were made the FY2025 Proposed Budget since the budget discussion at the September 3, 2024 Council Meeting.
Fund 501:
1. 501-000-5702-00 W22A Downtown Water Plant (WP #1) - Added $100,000 for potential change orders/contingencies
2. New McKinnon Water Plant - Reduced from $1,560,000 to $1,320,000 (Design)
3. WW25A Houston Lift Station & Harris St. Gravity Line Replacement - Increased from $534,000 to $600,000 (Design)
4. New Katy -Fulshear Lift Station Expansion - Increased from $230,000 to $430,000 (Design)